Families, Children & Learning – Capital Budget Summary

 

Forecast Variance Month 9

Service

Reported Budget Month 9

Reported at Other Committees/ IFRS Changes

New Schemes

Variations, Slippages & Reprofiles

Reported Budget Month 12

Provisional Outturn

Provisional Variance

Provisional Variance

£'000

£'000

£'000

£'000

£'000

£'000

£'000

£'000

%

0

Director of Families, Children & Learning

0

0

0

0

0

0

0

0.0%

0

Health, SEN & Disability Services

0

0

0

0

0

0

0

0.0%

0

Education & Skills

9,686

(629)

0

(722)

8,335

8,332

(3)

0.0%

0

Schools

453

0

0

(263)

190

151

(39)

-20.7%

(35)

Children's Safeguarding & Care

35

0

0

(35)

0

0

0

0.0%

0

Quality Assurance & Performance

0

0

0

0

0

0

0

0.0%

(35)

Total Families, Children & Learning

10,174

(629)

0

(1,020)

8,525

8,483

(42)

-0.5%

 

Details of Variation requests and explanations of significant Forecast Variances, Slippage or Reprofiles are given below:

 

Detail Type

Amount
£'000

Project

Description

Education & Skills

 

 

IFRS Changes

(386)

Capital Maintenance Adjustments

See paragraph 8.1 of the main report for a general explanation of IFRS changes.

IFRS Changes

(60)

New Pupil Places (Basic Need)

See paragraph 8.1 of the main report for a general explanation of IFRS changes.

IFRS Changes

(183)

Devolved Capital Adjustments

See paragraph 8.1 of the main report for a general explanation of IFRS changes.

Reprofile

(310)

New Pupil Places (Basic Need)

A reprofile of the New Pupil Places budget into 2023/24 was reported at TBM Month 9 whilst a major SEND project and Longhill school projects faced delays due to design and procurement works. Final design works are now underway and are due to be completed summer 2023. The remainder of the budget for 2022/23 associated with these contracts will need to be reprofiled into future years.

Reprofile

(218)

Universal Free School Meals

The projects were delayed due to an unforeseen lack of resource to scope requirements and contractor’s availability due to a backlog of works.

Reprofile

(23)

Devolved Formula Capital 2020/21

Minor reprofiling.

Reprofile

(236)

Devolved Formula Capital 2021/22 and 2022/23

Devolved Formula Capital is a financial resource that is devolved to schools by the Local Authority. Schools have the option to accrue the money for a maximum of 3 years and are able to request their allocation at any time. Funds that are not drawn down in year are reprofiled into future years for use.

Reprofile

(697)

Devolved Formula Capital Additional 2022/23

Additional announcement of DFC from DfE of £1.013m was announced in December 2022. This was intended to be released to schools for funding to improve energy efficiency in 2022/23. With a relatively short amount of time to meet spend the budget is requested to be reprofiled in 2023/24 to enable delivery of the plans.

Reprofile

29

High Needs Provision Capital

Minor reprofiling.

Reprofile

745

Education Capital Maintenance 2019/20 to 2022/23

A reprofile of the Capital Maintenance budget into 2023/24 was reported at TBM Month 9 due to a number of contracts awarded for several projects which span two to three financial years. Some of these projects have caught up in progress during the remainder of 2022/23, while others have been delayed due to the pandemic and supply chain delivery issues. A reprofile into 2023/24 is required to meet the carried over expenditure.

Slippage

(12)

Improvements to Early Years Settings

Minor slippage.

Variance

(2)

Education Capital Maintenance 2018/19

Minor underspend variance.

Variance

(1)

Devolved Formula Capital 2018/19

Minor underspend variance.

Schools

 

 

 

Reprofile

(95)

Impulse Education Management System

Minor reprofiling.

Slippage

(136)

Stanford Schools Window Replacement

The window replacement programme has been planned in two phases for 2022/23 and 2023/24.

Variation

(71)

Middle Street Primary School Entrance & Fencing

Minor underspend variance.

Children's Safeguarding & Care

 

Slippage

(35)

Sellaby House Enhancements (Contact Supervision Centres)

Minor slippage.

 

 

 

 

 


Health & Adult Social Care – Capital Budget Summary

 

Forecast Variance Month 9

Service

Reported Budget Month 9

Reported at Other Committees/ IFRS Changes

New Schemes

Variations, Slippages & Reprofiles

Reported Budget Month 12

Provisional Outturn

Provisional Variance

Provisional Variance

£'000

£'000

£'000

£'000

£'000

£'000

£'000

£'000

%

58

Adult Social Care

455

0

0

28

483

483

0

0.0%

0

Integrated Commissioning

0

0

0

0

0

0

0

0.0%

0

S75 Sussex Partnership Foundation Trust (SPFT)

0

0

0

0

0

0

0

0.0%

0

Public Health

0

0

0

0

0

0

0

0.0%

58

Total Health & Adult Social Care

455

0

0

28

483

483

0

0.0%

 

Details of Variation requests and explanations of significant Forecast Variances, Slippage or Reprofiles are given below:

 

Detail Type

Amount
£'000

Project

Description

Adult Social Care

 

 

Slippage

(16)

Knoll House Building Works

Minor slippage.

Variation

36

Adaptations to Homes of Disabled People (Better Care Fund/DFG)

Minor overspend variance.

Variation

8

Telecare (Better Care Fund/DFG)

Minor overspend variance.

 

 

 

 

 


Economy, Environment & Culture (excluding Housing Revenue Account) – Capital Budget Summary

 

Forecast Variance Month 9

Unit

Reported Budget Month 9

Reported at Other Committees/ IFRS Changes

New Schemes

Variations, Slippages & Reprofiles

Reported Budget Month 12

Provisional Outturn

Provisional Variance

Provisional Variance

£'000

£'000

£'000

£'000

£'000

£'000

£'000

£'000

%

0

Transport

19,484

21

0

(7,938)

11,567

11,198

(369)

-3.2%

0

City Environmental Management

8,378

0

200

(2,863)

5,715

5,715

0

0.0%

0

City Development & Regeneration

19,983

0

0

(4,524)

15,459

15,459

0

0.0%

0

Culture, Tourism & Sport

9,078

196

0

100

9,374

9,291

(83)

-0.9%

0

Property

4,948

0

0

98

5,046

5,046

0

0.0%

0

Total Economy, Environment & Culture

61,871

217

200

(15,127)

47,161

46,709

(452)

-1.0%

 

Details of Variation requests and explanations of significant Forecast Variances, Slippage or Reprofiles are given below:

 

Detail Type

Amount
£'000

Project

Description

Transport

 

 

 

Reported at Other Committees

20

CNF - Western Road Improvement Project

Reported at Other Committees

1

CNF - Norton Road Rain Gardens

Reprofile

(1,817)

Bridge Strengthening and Assessment

The budget is used for all the council’s structural highways work. The underspend is due to a number of issues: 1) Change in personnel. Staff members leaving and difficulty in recruitment. 2) Due to the lack of resources and commitment to support other projects such as Shelter Hall. 3) The current spend relates to design fees, so work is progressing, but not at the rate originally planned.

Reprofile

(1,749)

Integrated Transport Schemes (LTP)

The Cycle Network project will need to reprofile unspent budget as it is directly related to match funding schemes that are funded by ATE [Active Travel]. The Walking Networks Freestanding Crossings project budget also needs to be reprofiled as Members and consultees rejected the original plans. Work to redirect to other schemes has led to an underspend of the budget allocated for 2022/23.

Reprofile

(1,409)

Sustainability and Carbon Reduction Investment Fund Transport Projects

The budget of £3.9m was allocated to transport related projects within the budget process and has progressed reasonably well with a number of schemes completed. The investment  is also built into other transport related schemes and relies on those schemes progressing.

Reprofile

(1,327)

DfT Challenge  Fund - Western Road

Construction commenced in November 2022. This funding is committed and it is expected that it will be spent within 2023/24. There was a need to wait to spend the maintenance funding to coordinate as one project with the Active Travel and Bus Service Improvement Plan funding.

Reprofile

(500)

Bus Service Improvement Scheme (BSIP)

Construction is underway, however, following a significant amount of public interest in the construction management, including rerouting of buses, and political sensitivity, Transport Services have had to review the project phasing. Resources are therefore being focused on the western section of Western Road so the road can reopen sooner. The BSIP funded element (Dyke Road) will then follow on later this year instead.

Reprofile

(325)

Valley Gardens Phase 3 (LTP)

This project is supported by Local Growth Fund capital grants. Detail design works have been completed and the procurement of contractors is underway. Construction is expected to commence in October 2023 through to May 2025.

Reprofile

(237)

Exhaust Converters on Older Buses

50% of the purchase order was invoiced to bus operators to commence exhaust upgrades on buses. The second 50% is scheduled for 2023/24 on full completion of the project, including operator funded bus upgrades.

Reprofile

(206)

Active Emergency Travel Fund - Tranche 2

The funding identified to deliver A259 has been delayed due to a new framework contract set up and a new procurement process.

Reprofile

(202)

Climate Assembly Action Capital Investment Fund Transport Projects

The budget of £1.4m was allocated to transport related projects within the budget process and schemes have now been identified to support public transport services, mobility hubs, and low traffic and pedestrianised communities. The majority of the work is due to commence in 2023/24 and a large part of the budget has already been reprofiled into this year, the remainder for 2022/23 is now required to be reprofiled into 2023/24 as well.

Reprofile

(163)

CNF - Traffic Signal Carbon Reduction Programme

Around £0.132m of the works had been completed before the end of March but agreement to pay the invoices is yet to be concluded. The works were 99% complete, are switched on and working but payment is withheld pending some minor defects that need to be corrected. The program was delayed due to the roll out of the council’s new civils contract which interrupted procurement of civils contractors. Installation has now commenced and are due to complete the whole works by December 2023.

Reprofile

(160)

CNF - Air Quality Monitoring Transport & Travel

This is a two year project and funds are required to be carried over to 2023/24.

Reprofile

(140)

Safer Streets Fund Streetlighting

The intended work for the safer street projects has been delayed whilst teams have continued to identify appropriate plans and sites. Initially there were several projects that were hoping to be funded, due to staff changes and delayed decisions a full revision of how the safer street fund was to be spent was necessary. A revised plan to refurbish lanterns in the Royal Pavilion Gardens has now been committed following an unexpectedly lengthy agreement process. The hope is to have the restoration of the lanterns in the Royal Pavilion Gardens completed and billed by October 2023.

Reprofile

(118)

Valley Gardens Phase 1&2 (LTP)

Funding was allocated towards the contractors claim and retention fees which were not resolved until the end of the financial year. This will now be settled in the new financial year.

Reprofile

(103)

Air Quality Monitoring & Public Engagement

Payment for projects across Sussex have been processed in 2022/23 as scheduled. Brighton & Hove portions are pending procurement agreements. Further payments are scheduled on installation of equipment in 2023/24.

Reprofile

(86)

CNF - Electrical Vehicle Fast Charger Installations & Access

Minor reprofile under £0.100m.

Reprofile

(64)

Structural Maintenance of Carriageways

Minor reprofile under £0.100m.

Reprofile

(50)

CNF - Electric Vehicle Fast Chargers

Minor reprofile under £0.100m.

Reprofile

(50)

CNF - Air Quality Automatic Analysers

Minor reprofile under £0.100m.

Reprofile

(50)

Seafront Heritage Lighting Renewal Programme

Minor reprofile under £0.100m.

Reprofile

(45)

CNF - E-Cargo Accelerator Project

Minor reprofile under £0.100m.

Reprofile

(36)

CNF - Preston Park Sustainable Drainage System (SuDS)

Minor reprofile under £0.100m.

Reprofile

(15)

Major Projects (LTP)

Minor reprofile under £0.100m.

Reprofile

(9)

CNF - Eldred Avenue Sustainable Drainage System (SuDS)

Minor reprofile under £0.100m.

Reprofile

(1)

CNF - A270 Wild Park Rainscape

Minor reprofile under £0.100m.

Reprofile

75

School Streets

Minor reprofile under £0.100m.

Reprofile

121

Brighton Marina to River Adur Works

As reported at TBM Month 9, over £1.6m was reprofiled into 2023/24 to fund the programme which is to run from May 2023 for three years. Some preparatory defence works were delivered toward the end of 2022/23 and required a reprofile back into that financial year.

Reprofile

423

Brighton Bikeshare Replacement Programme

The Brighton Bikeshare Replacement Programme was reprofiled into 2023/24 and 2024/25 to reflect the expected delivery of the project. Progress was made during the later part of 2022/23 and a reprofile back for a part of the budget is required to meet those costs.

Reprofile

551

Street Lighting Maintenance (LTP)

As reported at TBM Month 9, over £2.2m was reprofiled into 2023/24 to 2025/26 to reflect the revised three-year timetable of the project. Some additional work was delivered toward the end of 2022/23 and required a reprofile back into that financial year.

Slippage

(134)

Citywide Strategic Transport Model

Whilst the majority of the budget for the delivery of the Citywide Strategic Transport Model was reprofiled at TBM Month 9 into 2023/24, a budget was retained in 2022/23 to meet initial costs as the delivery of the scheme proceeds. The project has yet to commence and will now be profiled to start in 2023/24.

Slippage

(106)

Low Traffic Neighbourhoods

There have been delays in developing plans and the project is expected to commence in 2023/24.

Slippage

(91)

Innovate UK Double Socket Chargers

Minor slippage of under £0.100m

Slippage

(83)

Covered Cycle Racks

Minor slippage of under £0.100m

Slippage

(14)

North Street Environmental Improvement

Minor slippage of under £0.100m

Slippage

(8)

Active Emergency Travel Fund - Tranche 3

Minor slippage of under £0.100m

Slippage

(7)

Intelligent Transport Systems Phase 2

Minor slippage of under £0.100m

Slippage

(4)

Local Safety Schemes (LTP)

Minor slippage of under £0.100m

Variation

82

CNF - A270 Wild Park Rainscape

Overspend due to contractual cost pressures (inflation).

Variation

73

On Street Residential Chargepoint Scheme

Overspend due to contractual cost pressures (inflation).

Variation

46

Ultra Low Emissions Taxi Infrastructure Scheme

Overspend due to contractual cost pressures (inflation).

Variance

(126)

Traffic Control Centre & Offstreet Parking Equipment

A budget from capital borrowing was approved in 2019/20 for the provision of installation of car park and traffic control centre equipment. The scheme was finalised in year and the remaining budget no longer required.

Variance

(121)

London Road Car Park Works

Capital borrowing was undertaken in 2020/21 to support much needed improvement and health and safety works at the London Road Car Park site. The works have been finalised and the remining budget no longer required.

Variance

(36)

Purchase of vans for parking infrastructure team

Minor variance.

Variance

(32)

A259/West St Shelter Hall

Minor variance.

Variance

(30)

Public Conveniences at Shelter Hall

Minor variance.

Variance

(12)

Controlled Parking Schemes

Minor variance.

Variance

(11)

Innovate UK Bookable Charging Points

Minor variance.

Variance

(1)

Safer Routes to Schools

Minor variance.

City Environmental Management

 

Reprofile

(1,632)

Procurement of Vehicles

Investment and replacement for a carbon neutral fleet. Orders placed but there is a delay in supply specifically for waste collection vehicles of which there are few suppliers.

Reprofile

(813)

Public Conveniences

Project was partly delayed depending on the outcome of budget setting around public toilets. The remining budget will now be reprofiled in 2023/24 in line with the programme delivery.

Reprofile

(230)

Stanmer Park restoration Fund HLF

Negotiation on Final Account settlement are still underway and will be resolved in 2023/24.

Reprofile

(150)

Pavilion and Mess Room Refurbishment Programme

Some delays in the programme due to officer capacity – new programme manager in recruitment.

Reprofile

(70)

CNF - Hollingdean Depot HGV EV Infrastructure

Minor reprofiling required.

Reprofile

(64)

CNF - Allotments Water Infrastructure Upgrade

Minor reprofiling required.

Reprofile

(61)

CNF - Wildlife and Wild-Flowers in Grass Verges

Minor reprofiling required.

Reprofile

(40)

CNF - Solar Panels at Stanmer Workshop

Minor reprofiling required.

Reprofile

(22)

CNF - Electrical Vehicle for Waterhall

Minor reprofiling required.

Reprofile

(18)

Stanmer Park Road

Minor reprofiling required.

Reprofile

(13)

Tennis Courts Upgrade Programme

Minor reprofiling required.

Reprofile

(7)

CNF - Community Composting

Minor reprofiling required.

Reprofile

(3)

CNF - St Ann's Well Café Sustainable Improvements

Minor reprofiling required.

Reprofile

22

CNF - Decompaction Machine for Grassed Areas

Minor reprofiling required.

Reprofile

35

Stanmer Park Offices

Minor reprofiling required.

Reprofile

39

CNF - Food Drainage Systems for Parks Tree Pits

Minor reprofiling required.

Reprofile

60

Parks and Open Spaces Investment

Minor reprofiling required.

Reprofile

70

Playground Refurbishment programme 2021-2025

Minor reprofiling required.

Reprofile

131

CNF - Woodland Creation Scheme

Project partly reprofiled into 2023/24 earlier in the year due to delays, however spend picked up in the later part of the year resulting in more budget to be drawn back from future years.

Reprofile

255

Stanmer Depot relocation

Work was anticipated to be completed early April, and the budget was reprofiled accordingly, but part payment was required in March hence a reprofile back into 2022/23 is required.

Slippage

(100)

CNF - Electrical Infrastructure at City Parks Fleet

The wider construction project timeline has shifted back due to technical complexities.

Slippage

(59)

Citywide Street Investment

Minor slippage.

Slippage

(28)

Holingdean Deport Office Accommodation

Minor slippage.

Variation

(259)

Playground Refurbishment programme 2021-2025

The Playground Refurbishment Programme was approved in 2021/22 as part of a 5-year £2.447m ongoing refurbishment and replacement. The programme is being met from a combination of borrowing, Section 106 and revenue contributions. Service revenue contributions for 2022/23 from maintenance budgets were reduced to meet the lower in year spend.

Variation

75

MUGA at Stoneham Park

Overspend due to contractual cost pressures (inflation).

Variation

12

CNF - Wilding Waterhall

Minor variation.

Variation

7

Saunders Park Playground

Minor variation.

City Development & Regeneration

 

Reprofile

(4,831)

Black Rock Enabling Works

The project is funded with support from Local Growth Fund capital grant. Work has progressed well during 2022/23 and the project is expected to be finalised mid 2023/24. The remainder of the budget will be reprofiled into 2023/24

Reprofile

(436)

Madeira Terraces Crowd Funding Contribution

Crowdfunding resources are held within the Capital Investment Programme to support the Madeira Terraces regeneration project. The construction phase is due to commence in 2023/24 and this budget will be incorporate into that timetable.

Reprofile

(290)

Madeira Terraces Regeneration - Carbon Neutral Fund

A contribution from the Carbon Neutral Fund was released in 2021/22 to support increased biodiversity and the sustainable use of materials throughout the regeneration project. The budget has been incorporated into the timetable for the construction period which will be during 2023/24 and 2024/25.

Reprofile

(142)

Brighton Research & Innovation Fibre Ring

The project is supported by grant funded from the Getting Building Fund and is in partnership with Mid Sussex District Council. A total of £1.440m grant has been received with the majority of expenditure incurred in 2022/23. The project is due to complete early in 2023/24.

Reprofile

(33)

Eastern Seafront Masterplan

Minor reprofiling required.

Reprofile

(33)

Full Fibre Network

Minor reprofiling required.

Reprofile

(12)

Falmer Released Land

Minor reprofiling required.

Reprofile

(5)

Circus Street Redevelopment - LGF

Minor reprofiling required.

Reprofile

(3)

Redevelopment of King Alfred Swimming Pool

Minor reprofiling required.

Reprofile

(1)

Sustainability & Carbon Reducion Investment Fund

Minor reprofiling required.

Reprofile

759

Madeira Terraces Regeneration - Project Support

The Madeira Terraces project is scheduled for construction to commence in quarter 1 of 2024 until quarter 4 2025. The project is due to enter the procurement tender process in early to mid-2023. Corporate funding from capital receipts and reserves was approved to support the design and procurement phase and a reprofiled from 2023/24 is required to meet the costs incurred in 2022/23.

Variation

(12)

Falmer Released Land

Minor variation.

Variation

(4)

Contribution to Housing JV

Minor variation.

Variation

7

Black Rock Enabling Works

Minor variation.

Variation

8

Eastern Seafront Masterplan

Minor variation.

Variation

11

Waterfront Redevelopment

Minor variation.

Variation

12

Circus Street Development

Minor variation.

Variation

17

Seafront Investment Programme Landscaping

Minor variation.

Variation

28

Madeira Terraces Regeneration - Project Support

Minor variation.

Variation

32

Redevelopment of King Alfred Swimming Pool

Minor variation.

Variation

36

New England House

Minor variation.

Variation

70

i360 Project

Minor variation.

Variation

124

SCAPE Water Level Protection Carden Avenue & Norton Rd

The Water Level Protection scheme was forecast to commence in 2023/24 with a budget supported by the award of Environment Agency and SCAPE Interreg grant together with match funding from the council. Work has commenced on the project in 2022/23 hence a reprofile back of the budget to meet costs incurred.

Variation

174

Brighton Research & Innovation Fibre Ring

The project is supported by grant funded from the Getting Building Fund and is in partnership with Mid Sussex District Council. A total of £1.440m grant has been received with an additional allocation of £0.174m awarded in 2022/23 to enable the completion of the project.

Culture, Tourism & Sport

 

 

Reported at Other Committees

196

Royal Pavilion Estate Development (Phase 2 Gardens)

Capital grant funding of £0.214m from the National Heritage Lottery Fund has been awarded to the development and submission of the Round 2 funding bid for the Phase 2 works. The initial tranche has been received in 2023/24. The preparatory work has commenced in 2022/23 and will continue into 2023/24 for final submission of a business case for an application of grant funding up to circa £3.4m

Reprofile

(198)

Royal Pavilion Estate (Phase 1)

The Phase 1 works are due for Practical Completion in the first quarter of 2023/24. Whilst the majority of the budget was profiled for 2022/23 there will be a requirement for the balance from 2022/23 to be profiled into 2023/24 to meet the remaining costs, defects and retentions.

Reprofile

(18)

Royal Pavilion Estate Development (Phase 2 Gardens)

Minor reprofiling required.

Reprofile

(10)

Levelling Up Fund - Kingsway to the Sea

Minor reprofiling required.

Slippage

(250)

Seafront Railings & Beach Hut Replacement

Agreement from committee was approved in November 2022 with the last few months finalising the design and planning processes. Works are now committed for 2023/24.

Slippage

(98)

Prince Regent - Replace Mechanical Equip

Minor slippage.

Slippage

(70)

Prince Regent Entrance

Minor slippage.

Slippage

(50)

Withdean Sports Complex - 3G Development

Minor slippage.

Slippage

(48)

Withdean Sports-Soft play Development

Minor slippage.

Slippage

(30)

King Alfred Main Pool Reinforcement

Minor slippage.

Slippage

(29)

B&H Welcome Gateway Train Stations

Minor slippage.

Variation

(4)

Prince Regent Entrance

Minor variance.

Variation

1

Replacement Seating Brighton Centre

Minor variance.

Variation

4

Kings Road Paddling Pool

Minor variance.

Variation

5

Disabled Access Beach Ramp

Minor variance.

Variation

7

Hove Beacon Lighting Scheme

Minor variance.

Variation

21

Levelling Up Fund - Kingsway to the Sea

Minor variance.

Variation

867

Royal Pavilion Estate (Phase 1)

Additional funding support of £0.5m from Arts Council England was awarded in 2022/23 to enable completion of the project. An insurance reclaim payment from storm damage settled during 2022/23 has also been included in the overall budget to meet repair works that was incorporated into the programme timetable.

Variance

(83)

Saltdean Lido Restoration

Less than £0.100m variance.

Property

 

 

 

Reprofile

(135)

Victoria Fountain Repairs

Project was delayed due to unforeseen circumstances including difficulty for securing a suitable cost to install the pumps, pipework distribution and control equipment for the fountain itself.

Reprofile

(105)

Royal Pavilion External Repairs

The scope of works has been extended substantially by the Royal Pavilion & Museum Trust. The work is now in progress and will continue into 2023/24.

Reprofile

(83)

Building Security

Minor reprofiling required.

Reprofile

(26)

Window Replacement Cottages Property Portfolio

Minor reprofiling required.

Reprofile

(25)

CNF - Commercial Portfolio Energy audits & improvements

Minor reprofiling required.

Reprofile

(24)

CNF - Water Efficiency Fund

Minor reprofiling required.

Reprofile

(3)

CNF - Provision of Drinking Water Fountains and Bottle Filling Points

Minor reprofiling required.

Reprofile

2

King Alfred Cathodic Protection System Repairs

Minor reprofiling required.

Reprofile

10

CNF - Decarbonised Heat Pilots/Heat Pumps

Minor reprofiling required.

Reprofile

15

Commercial Property Portfolio Repairs

Minor reprofiling required.

Reprofile

21

External Improvement Works

Minor reprofiling required.

Reprofile

29

Workstyles Phase 4

Minor reprofiling required.

Reprofile

55

Stanmer Park Agricultural Buildings

Minor reprofiling required.

Reprofile

136

Madeira Terrace Structural Repairs

Budget was reprofiled to 2023/24 earlier in the financial year, however, the contractor managed to deliver within the financial year, so required to reprofile budget back again into 2022/23.

Reprofile

499

Moulsecoomb Hub and Housing – Workstyles 4

The Moulsecoomb Hub has a budget of circa £17m. The majority of the budget is profiled for the construction period 2023/24 to 2024/25 although costs have been incurred in 2022/23 in relation to design, master planning, cost advisors, and technical fees as well as the associated land sites that will transfer to the HRA to enable the delivery of the housing.

Slippage

(58)

Corporate Fire Risk Assessments

Minor slippage.

Slippage

(57)

New England House Fire Improvements

Minor slippage.

Slippage

(49)

Energy Certificates Corporate Buildings

Minor slippage.

Slippage

(29)

Asbestos Surveys

Minor slippage.

Slippage

(28)

BTH - PMB contribution to refurbishment

Minor slippage.

Slippage

(27)

Barts House - Cladding & Window Replacement

Minor slippage.

Slippage

(27)

Hollingdean Depot Workstyles 4

Minor slippage.

Slippage

(23)

Barts House Trickle Vent Installation

Minor slippage.

Slippage

(19)

Hollingdean Lane Phase 1 Repair Wall

Minor slippage.

Slippage

(16)

Brighton Centre Lift Refurbishment

Minor slippage.

Slippage

(15)

Brighton Centre Roofing works

Minor slippage.

Slippage

(11)

Legionella Works

Minor slippage.

Slippage

(10)

Environment Residential Properties Repairs & Improvements

Minor slippage.

Slippage

(8)

Hove Floral Clock Fencing

Minor slippage.

Slippage

(7)

Hove Town Hall Building Management System (BMS)

Minor slippage.

Slippage

(5)

Statutory DDA Access Works Fund

Minor slippage.

Slippage

(2)

Barts House Mechanical Ventilation

Minor slippage.

Variation

(17)

Window Replacement Cottages Property Portfolio

Minor variation.

Variation

(11)

Fire Safety Improvements

Minor variation.

Variation

(5)

Mechanical Boiler Replacement

Minor variation.

Variation

(1)

Passenger Lift H&S Works

Minor variation.

Variation

1

Hollingdean Depot Health & Safety

Minor variation.

Variation

2

Portslade Sixth Form Conversion - Workstyles 4

Minor variation.

Variation

4

Weald Avenue Allotments Water Main

Minor variation.

Variation

5

BTH Flat Roof

Minor variation.

Variation

8

Misc Internal Refurbishments

Minor variation.

Variation

8

Moulsecoomb Hub and Housing – Workstyles 4

Minor variation.

Variation

9

External Improvement Works

Minor variation.

Variation

13

Hove Library Phase 1 Roof Repairs & External Redecoration

Minor variation.

Variation

107

Commercial Property Portfolio Repairs

Maintenance reserves have been incorporated into the commercial property repairs capital budget for 2022/23 to enable the progression of repairs that will significantly enhance the property portfolio’s commercial income.

 

 

 

 


Housing, Neighbourhoods & Communities (excluding Housing Revenue Account) – Capital Budget Summary

 

Forecast Variance Month 9

Unit

Reported Budget Month 9

Reported at Other Committees/ IFRS Changes

New Schemes

Variations, Slippages & Reprofiles

Reported Budget Month 12

Provisional Outturn

Provisional Variance

Provisional Variance

£'000

£'000

£'000

£'000

£'000

£'000

£'000

£'000

%

(140)

Housing General Fund

5,476

542

0

(80)

5,938

5,440

(498)

-8.4%

0

Libraries

0

0

0

0

0

0

0

0.0%

0

Communities, Equalities & Third Sector

0

0

0

0

0

0

0

0.0%

0

Safer Communities

0

0

0

0

0

0

0

0.0%

(140)

Total Housing, Neighbourhoods & Communities

5,476

542

0

(80)

5,938

5,440

(498)

-8.4%

 

Details of Variation requests and explanations of significant Forecast Variances, Slippage or Reprofiles are given below:

 

Detail Type

Amount
£'000

Project

Description

Housing General Fund

 

 

Reported at Other Committees

542

Brittany Road Purchase Loan

Long term debtor loan reported to P&R Committee December 2022.

Reprofile

(149)

Disabled Facilities Grants

Delays in spend caused largely by shortage of capacity in framework contractors.

Reprofile

59

Warm Safe Homes Grant

Minor reprofiling required.

Reprofile

10

Brighton & Hove Warmer Homes Investment Fund

Minor reprofiling required.

Variance

(302)

LDV On-Going Costs - Community Homes (B&HSCH)

The amount of capital works for the 499 Seaside Homes Properties varies from year to year depending on the HRA capital programme and the works due for seaside homes properties. Any reprofiling of the HRA capital programme will have an impact on the in-year spend for Seaside homes properties. For 2022/23, only £0.098m was required to fund these works.

Variance

(196)

Rough Sleeper Accommodation Programme (RSAP) 10 Year leased

30 properties were purchased under 10 year leases, part funded by the Rough Sleeper Accommodation Programme (RSAP) grant from Homes England. The underspend reflects that the costs of these was less than budgeted and therefore reduces the amount of borrowing required by the council.

 

 

 


Housing Revenue Account (HRA) – Capital Budget Summary

 

Forecast Variance Month 9

Unit

Reported Budget Month 9

Reported at Other Committees/ IFRS Changes

New Schemes

Variations, Slippages & Reprofiles

Reported Budget Month 12

Provisional Outturn

Provisional Variance

Provisional Variance

£'000

£'000

£'000

£'000

£'000

£'000

£'000

£'000

%

2,019

City Development & Regeneration

4,476

0

0

24

4,500

6,755

2,255

50.1%

(2,789)

Housing Revenue Account

76,732

0

0

(7,514)

69,218

65,294

(3,924)

-5.7%

(770)

Total Housing Revenue Account

81,208

0

0

(7,490)

73,718

72,049

(1,669)

-2.3%

 

Details of Variation requests and explanations of significant Forecast Variances, Slippage or Reprofiles are given below:

 

Detail Type

Amount
£'000

Project

Description

City Development & Regeneration

 

Reprofile

24

Windlesham Close

Minor reprofile required.

Variance

2,267

Victoria Road

The overspend of £2.267m on the original approved budget, relates to the total project costs for both the Sports Pavilion and Housing schemes. 60% of the overspend is attributable to overruns in the construction costs above the Agreed Maximum Price for both the Sports Pavilion and Housing Scheme. Both schemes have been constructed during a time of great uncertainty as a result of Brexit, the Pandemic and the war in the Ukraine, which is having a considerable impact on the UK economy and the construction market. This, together with the tightening up of Fire Safety Regulations post Grenfell, has significantly contributed to the uplift in project costs. The remaining 40% of the overspend is attributable to the extra professional fees associated with the detailed design stages of the Housing scheme. The scheme has required greater design coordination from the Lead Architect and input from specialist designers than was originally anticipated. A summary of Lessons Learnt on the project has been shared with the Housing Supply Programme and Members Boards as well as the council’s Strategic Construction Partnership with Morgan Sindall.

Variance

2

Feasibility and Design - Housing Invest

Minor variance.

Variance

(10)

Selsfield Drive

Minor variance.

Variance

(4)

Buckley Close

Minor variance.

Housing Revenue Account

 

 

Reprofile

(4,110)

Home Purchase Scheme

The budget was not fully spent this year due to the number of completions for the home purchase scheme not reaching the target number. This is due to less properties becoming available to assess and purchase over the year. However, additional commitments were made during quarter 4 of 2022/23 with the completions for these properties due to take place early in 2023/24. 

Reprofile

(1,771)

Housing Joint Venture purchases

Due to an exemption being permitted relating to the payment of Stamp Duty Land Tax the project is currently estimated to underspend against the approved budget. Stamp Duty Land Tax was expected to be incurred in quarter 4 of 2022/23. The budget will be reprofiled into 2023/24 to ensure budget is available for any unexpected cost overruns.

Reprofile

(515)

New Housing Works Management System

Spend for this financial year was still largely centred around the project teams costs. The budget is required for future years delivery costs.

Reprofile

(272)

Housing First

The RSAP project is on track to deliver against DLUCH milestones with a number of purchases due to be made in 23/24. It is also anticipated that there will be an underspend in the budget due to the cost of individual properties differing. The final outturn will not be known until the last purchase is made.  

Reprofile

(243)

New Housing Asset Management System

Spend for this financial year was still largely centred around the project teams costs. The budget is required for future years delivery costs.

Reprofile

(208)

Palace Place redevelopment

The development at Palace Place was delayed during 2022/23, it is expected that project will start on site during 2023/24. Costs and funding are being reviewed to ensure value for money is still being achieved.

Reprofile

(180)

Energy Efficiency

Revised timelines in confirming the design of a new low carbon heating and hot water system means that this project will now be completed in the first quarter of 2023/24.

Reprofile

(177)

Converting Spaces in Existing Buildings

Delivery of the hidden homes projects spans a number of financial years, this reprofile matches the expected profile of spend for the programme which continues into 2023/24.

Reprofile

(80)

EV Fast Charging Points – Housing

Minor reprofile required.

Reprofile

22

Moulsecoomb Hub - Housing

Minor reprofile required.

Reprofile

15

Design Competition

Minor reprofile required.

Reprofile

3

Eastergate Road

Minor reprofile required.

Reprofile

2

Frederick Street

Minor reprofile required.

Variance

(655)

Kitchens

There has been a significant underperformance by the planned works contractor for kitchen and bathroom replacements which has resulted in an underspend. To address this performance issue going forward, approval was given by Housing Committee (16th November 2022) to procure up to two further contractors for this work stream and an improved spend against this budget should be seen next financial year.

Variance

(635)

HRA Adaptations

The underspend is due to several variables, mainly planning delays and contractor capacity (high demand for builders).

Variance

(391)

Energy Efficiency

Revised timelines in confirming the design of a new low carbon heating and hot water system means that this project will now be completed in the first quarter of 2023/24.

Variance

(354)

Windows

Consultants have been appointed to undertake the drawings and specifications for timber windows programme, these will be provided in batches and when received will be tendered through our Lot 2 framework.

Variance

(348)

Fire Safety

Reduced spend due to the revised timescales in staff recruitment and the impact on both the commencement of the additional resource requirements and addressing of the contractor requirements.

Variance

(267)

Communal Fire Alarms

Resourcing gap and the lack of a contractor has led to a reduced spend this financial year.

Variance

(265)

Door Entry Systems & CCTV

The door entry contract was at an end in 2022 and engagement in the procurement exercise for the contract minimised the opportunities to fulfil the full budget allowance.

Variance

(242)

Doors

A change in the door supplier used by the contractor for these works and the need to re-survey properties has led to a reduced spend for this financial year.

Variance

(239)

Main Entrance Doors

Due to manufacturing costs increasing steadily over the last year Housing are working on a revised procurement timeline to use an existing framework with another provider.

Variance

(197)

Gladstone Court

The cost of works associated with the lift has been met from the main lifts programme. This is therefore a true underspend across the HRA capital programme.

Variance

(167)

Communal Rewire

There was an increased spend against re-wires, due to inflation and the impact of the testing program, resulting in more works than in previous years.

Variance

(143)

Feasibility and Design - P&I

There was less spend than budgeted for against consultancy and feasibility surveys in respect of major projects.

Variance

(138)

Car Parks & Garages

There was less resurfacing and relining works carried out during the year than allowed for in the budget.

Variance

(122)

Domestic Boiler and system installation

There was a small underspend against the installation budget.

Variance

(90)

Solar Panels

Minor variance.

Variance

(76)

Water Tanks

Minor variance.

Variance

(69)

External Decorations & Repairs

Minor variance.

Variance

(54)

Lightning Protection

Minor variance.

Variance

(41)

Upgrading Residential CCTV Systems

Minor variance.

Variance

(40)

Next Steps Accomodation Programme

Minor variance.

Variance

(33)

Communal Boilers

Minor variance.

Variance

(32)

Bathrooms

Minor variance.

Variance

(26)

Environmental Improvements

Minor variance.

Variance

(20)

HRA Owned Playgrounds Refurbishment

Minor variance.

Variance

(18)

Seniors Improvements

Minor variance.

Variance

(15)

Lifts

Minor variance.

Variance

(15)

Sheltered Services Systems

Minor variance.

Variance

(13)

New Housing Management ICT system

Minor variance.

Variance

(3)

Ventilation

Minor variance.

Variance

1

Housing Centre - Heating & Ventilation System

Minor variance.

Variance

3

Internal Decorations & Repairs

Minor variance.

Variance

3

Capital Works Assessment

Minor variance.

Variance

7

Minor Capital Works

Minor variance.

Variance

8

TV Aerials

Minor variance.

Variance

10

Roofing

Minor variance.

Variance

13

BHCC Projects

Minor variance.

Variance

19

Oxford Street

Minor variance.

Variance

23

Fencing

Minor variance.

Variance

51

Empty Properties

Minor variance.

Variance

56

City-Wide Loft Conv & Ext Project

Minor variance.

Variance

86

Structural Repairs

Minor variance.

Variance

198

Condensation & Damp Works

There has been a significant increase in damp and condensation cases reported in 2022/23. Cases have increased from 110 active cases in September 2022 to 1,337 active cases in May 2023. This increase is as a result of the increase in awareness following the tragic death in Rochdale and the impact of the fuel crises resulting in tenants reducing the energy used to heat their homes. The service has responded promptly to this issue engaging additional contractor resource to support our in-house resource. This spend has been used both to combat the initial impacts of damp and mould and provide additional resource to deal with material and structural defects which contribute to damp and condensation. Based on current trends spends at this level are likely to continue until some of the inherent defects in our stock are remedied. It has been necessary to use waivers for procurement due to the need to respond quickly, however the service intends to procure a framework over the summer period to ensure that the council is achieving value for money. Spend will be closely monitored through the TBM process but it is anticipated that there will be a similar level spend for the financial year 2023/24.

Variance

306

Domestic Rewire

There was an increased spend against domestic re-wires, due to inflation and the impact of the testing program, resulting in more works than in previous years.

 

 


Governance, People & Resources - Capital Budget Summary

 

Forecast Variance Month 9

Unit

Reported Budget Month 9

Reported at Other Committees/ IFRS Changes

New Schemes

Variations, Slippages & Reprofiles

Reported Budget Month 12

Provisional Outturn

Provisional Variance

Provisional Variance

£'000

£'000

£'000

£'000

£'000

£'000

£'000

£'000

%

0

Chief Executive Monitoring Office

0

0

0

0

0

0

0

0.0%

0

Policy & Communications

0

0

0

0

0

0

0

0.0%

0

Legal & Democratic Services

0

0

0

0

0

0

0

0.0%

0

Life Events

0

0

0

0

0

0

0

0.0%

0

Customer Modernisation & Data

0

0

0

70

70

70

0

0.0%

0

Finance

150

0

0

(81)

69

69

0

0.0%

0

Procurement

0

0

0

0

0

0

0

0.0%

0

HR & Organisational Development

190

0

0

(117)

73

73

0

0.0%

(115)

IT&D

1,717

0

0

259

1,976

1,976

(0)

0.0%

0

Welfare Revenue & Business Support

0

0

0

0

0

0

0

0.0%

0

Housing Benefit Subsidy

0

0

0

0

0

0

0

0.0%

0

Contribution to Orbis

0

0

0

0

0

0

0

0.0%

(115)

Total Governance, People & Resources

2,057

0

0

131

2,188

2,188

(0)

0.0%

 

Details of Variation requests and explanations of significant Forecast Variances, Slippage or Reprofiles are given below:

 

Detail Type

Amount
£'000

Project

Description

Customer Modernisation & Data

 

Variation

70

Carefirst Replacement Project

Minor variation.

Finance

 

 

 

Slippage

(81)

Enterprise Resource Planning Programme

Minor slippage.

HR & Organisational Development

 

Slippage

(117)

Replacement Learning Management System

Funding agreed for a three-year period, however, budget needs to be reprofiled in line with planned expenditure levels across the three years of the project.

IT&D

 

 

 

Reprofile

116

Wide Area Network - The Link (SEG)

Budget reprofiled at TBM9 was based on information from partners at ESCC. However, the amount needed to contribute to the core fibre build costs was higher in 2022/23 than advised so this led to the need to reprofile some budget back. The fibre build costs are still within budget but more was paid in 2022/23 than was expected at TBM9.

Reprofile

85

Digital Organisation Programme 2020

Minor reprofiling required.

Slippage

(36)

IT Equipment for Members

Minor slippage.

Variation

81

Digital Organisation Programme 2020

Minor variation.

Variation

13

IT Equipment - Future Ways of Working

Minor variation.

 

 

Note: There are currently no capital budgets to report on for Corporate Budgets.